Publié le 11 mars 2024

When a contractor fails to perform, the impulse to terminate immediately is a dangerous trap. Declaring a breach is not a single, aggressive action but a calculated sequence of defensive manoeuvres. The goal is not merely to end the contract, but to construct such a robust and well-documented legal position that the defaulting party is deterred from ever launching a wrongful termination—or repudiation—lawsuit against you. This guide outlines that precise, cautious sequence for Canadian project owners.

As a project owner, few situations are more frustrating than watching a contractor miss deadlines, deliver substandard work, or signal that they might not fulfil their obligations. The immediate, emotional response is often to declare a breach and terminate the agreement. However, acting rashly is one of the most significant strategic errors you can make. It risks placing you in the « repudiation trap »—where your own premature or improper termination is seen as a breach, exposing you to the very lawsuit you sought to initiate.

The conventional advice to « read your contract » and « document everything » is true, but it is tactically insufficient. It misses the critical element of timing and procedure. The correct approach is not about confrontation; it’s about building a fortress of evidence. It involves a deliberate, step-by-step process that demonstrates your reasonableness and gives the other party every contractually-required opportunity to remedy their failure. This transforms termination from a risky gamble into a legally sound final step.

This article moves beyond generic advice to provide a strategic roadmap. We will dissect the difference between a minor issue and a fundamental breach that justifies termination, outline the crucial notices you must send, and explain why your own conduct after a breach is just as important as the breach itself. By following this calculated sequence, you shift the legal risk squarely onto the defaulting party, protecting your project and your business.

To navigate this complex process, this article breaks down the essential steps and strategic considerations. The following sections will guide you through building your legal position, from initial assessment to final action, ensuring every move is deliberate and defensible.

Fundamental Breach vs Minor Warranty: When Can You Actually Cancel the Contract?

The right to terminate a contract does not arise from just any failure to perform. Canadian law makes a critical distinction between a « condition » and a « warranty. » A breach of warranty—a minor, non-essential term—only entitles you to claim damages. For example, if a contractor uses a brand of paint that is functionally identical but different from the one specified, it’s likely a breach of warranty. You can sue for any difference in value, but you cannot terminate the entire contract.

Termination is a remedy reserved for the breach of a condition, a term so vital it goes to the « root of the transaction. » This is often called a fundamental breach. It’s a failure so severe that it deprives the innocent party of substantially the whole benefit of the contract. As established in landmark Canadian cases like Hunter Engineering Co. v. Syncrude Canada Ltd., a breach of a condition is considered a ‘repudiation’ of the contract, giving you the choice to either accept it and end the contract, or affirm the contract and sue for damages.

Determining what constitutes a fundamental breach is highly fact-specific, but industry standards provide useful thresholds. These are not absolute rules, but they offer a lens through which a court might view the severity of a breach:

  • SaaS Contracts (Ontario): System downtime that exceeds 24 consecutive hours or a failure to meet a 99% uptime guarantee is often considered fundamental.
  • Construction Projects (Alberta CCDC): Delays that push the project timeline beyond 30% or a failure to meet critical structural specifications are strong candidates.
  • Supply Agreements: The non-delivery of goods that represent more than 25% of the total contract value would likely qualify.
  • Quebec Civil Code: Under Article 1604, you must prove the breached obligation was ‘essential’ and that the breach renders the contract’s purpose unattainable.

Before taking any action, your first step must be a dispassionate analysis: is this failure truly fundamental, or is it an inconvenience? Mistaking a minor warranty breach for a fundamental one and terminating the contract is the primary way project owners fall into the repudiation trap.

What to Do When a Supplier Says They « Might Not » Deliver Next Month?

Sometimes a breach is not a clear failure, but a worrisome signal. A supplier might state, « We’re having production issues and *might not* be able to deliver next month’s order. » This is not a present breach, but it is a potential future breach, known in law as anticipatory repudiation. It occurs when one party, by words or conduct, makes it clear they do not intend to perform their future obligations. You cannot sit and wait for the damage to occur; you must act strategically.

The correct legal tool in this scenario is not an immediate termination, but a formal demand for « adequate assurance of performance. » This is a written request that compels the other party to clarify their ambiguous statement. It forces them to either commit to performance or confirm their intention to breach, thereby solidifying your legal position. This is a critical part of building your paper trail fortress, demonstrating you acted reasonably to clarify the situation before taking drastic measures.

This image highlights the importance of organising all communications to build a coherent and documented record of events.

Close-up of hands organizing business documents and correspondence

A properly drafted request for assurance is a powerful defensive manoeuvre. It should not be an angry email but a formal letter containing specific elements to be legally effective:

  • Reference the specific contract clause that outlines the performance obligation in question.
  • Quote the supplier’s ambiguous communication verbatim, including the date and time it was received.
  • Demand clear, written assurance of their intent and ability to perform within a reasonable timeframe (e.g., 10 business days).
  • State the consequences of inaction: « Failure to provide such assurance by the specified date will be treated as an anticipatory repudiation of the contract. »
  • Send the letter via a trackable method, such as registered mail and email, to create a documented delivery trail.
  • For contracts governed by Quebec law, it’s wise to reference Articles 1590 and 1602 of the Civil Code concerning notification requirements.

This letter shifts the onus onto the supplier. If they provide assurance, you have a renewed commitment. If they fail to respond or confirm their inability to perform, you have now converted their ambiguity into a clear anticipatory breach, giving you solid grounds to terminate and seek alternative solutions.

The Duty to Mitigate: Why You Can’t Just Let Losses Pile Up After a Breach?

Once a breach occurs—whether actual or anticipatory—the law imposes a crucial obligation on the innocent party: the duty to mitigate. This means you must take reasonable steps to minimise your own losses. You cannot simply stand by, let damages accumulate, and then send the defaulting party an enormous bill. Canadian courts expect you to act promptly and commercially to limit the financial impact of the breach.

The consequences of failing to mitigate are severe. The Supreme Court of Canada has affirmed this principle repeatedly. In the landmark case of Southcott Estates Inc. v. Toronto Catholic District School Board, a purchaser’s damage award of nearly $2 million was reduced to a nominal $1 on appeal because they failed to seek alternative properties after the vendor breached. The court ruled that by not taking reasonable steps to find a replacement, the purchaser had failed in their duty to mitigate their own losses. This is a stark warning: your inaction can erase your right to compensation.

Reasonable mitigation efforts must begin promptly. While every case is different, Canadian courts typically consider reasonable mitigation efforts to begin within 24-30 days of becoming aware of the breach. This requires immediate, documented action. The best way to prove mitigation is by creating a detailed log of your efforts. This becomes a critical piece of evidence should the dispute proceed to litigation.

Your Action Plan: Creating a Mitigation Log for Canadian Courts

  1. Document all immediate actions taken to minimize losses within the first 7 days of the breach.
  2. Record every attempt to find alternative suppliers or contractors, including dates, contact details, and quotes received.
  3. Keep organised receipts for all expenses incurred during mitigation, such as costs for emergency suppliers or expedited shipping.
  4. Document why certain, more expensive mitigation options were rejected as commercially unreasonable.
  5. Maintain a clear and updated calculation of the accumulating losses, distinguishing between costs incurred and revenue lost.

The duty to mitigate is not a passive exercise. It is an active, ongoing process that demonstrates to a court that you have acted in good faith. By meticulously documenting your efforts to stem the financial bleeding, you strengthen your claim for the losses that were truly unavoidable.

The « Silence » Trap: How Ignoring a Breach Can Strip Your Right to Sue Later?

When faced with a minor but recurring breach—such as a contractor who is consistently a few days late with deliverables—the temptation is to let it slide to avoid confrontation. This is a strategic error known as the « silence trap, » or waiver by acquiescence. By repeatedly accepting defective performance without formally objecting, you risk sending a legal signal that you are waiving your right to enforce the original terms of the contract. If you later try to terminate based on this pattern of breaches, the other party can argue that you accepted this as the new standard of performance.

Furthermore, inaction has a strict deadline. You cannot wait indefinitely to act on a breach. Under Ontario’s Limitations Act, 2002, the basic limitation period for breach of contract claims is two years from the day the claim was discovered. Other provinces have similar limitation periods. Waiting too long means your right to sue evaporates completely, regardless of the merits of your claim.

The solution to this dilemma is not immediate escalation but strategic communication. You need to acknowledge the breach without terminating the contract, thereby preserving your rights for future action. This is achieved through a « Reservation of Rights » letter. This formal notice informs the other party that you are aware of their default, are choosing not to terminate at this moment, but are expressly not waiving any of your rights or remedies under the contract.

A Reservation of Rights letter is a critical piece of your legal armoury. It should be sent promptly after discovering a breach and must include these essential elements:

  • An explicit statement such as: « We hereby reserve all of our rights and remedies under the contract and at law. »
  • A factual acknowledgement of the specific breach without accepting it as grounds for immediate termination.
  • A clear statement that you are continuing performance on a temporary basis while you assess your options.
  • Inclusion of the phrase: « This communication is without prejudice to our right to terminate the contract for this or any future breach. »
  • A specified date for reassessment (e.g., 30 days) to create a deadline for improvement.

This letter puts the defaulting party on notice that their performance is under scrutiny, pressuring them to improve while protecting your legal position. It prevents your silence from being used against you later.

The 10-Day Cure Period: Why Sending the Default Notice is Critical Before Termination?

After you have assessed the breach as fundamental, reserved your rights, and the defaulting party has still failed to perform, you reach the final step before termination: the formal Notice of Default. This is arguably the most critical document in the entire sequence. Many contracts, particularly standard forms used in Canadian construction like the CCDC-2, contain a « cure period » clause. This clause requires the innocent party to provide formal written notice of the default and give the breaching party a specified period (e.g., 7 or 10 days) to « cure » or fix the problem.

Terminating the contract without providing this contractually mandated cure period is a fatal error. It can boomerang, turning your justified termination into a wrongful one (repudiation), making you the party in breach. Even if your contract doesn’t specify a cure period, providing one is a sign of commercial reasonableness that will be viewed favourably by a court. It demonstrates that your primary goal was performance, not termination.

Preparing this notice requires precision and a complete absence of emotional language. It is a factual, legal document, not a list of grievances.

Professional preparing formal business correspondence at office desk

A legally effective Notice of Default must be meticulously drafted to form the foundation of your termination. It should include the following critical components:

  • Cite the Breached Clauses: Reference the specific section numbers of the contract that have been breached.
  • Describe the Breach Factually: State the facts of the default clearly and objectively. For example, « As of October 26, milestone 3 remains incomplete, which is 15 days past the contractually stipulated deadline. »
  • State the Cure Period: Clearly state the deadline to cure the default. If the contract specifies a period, use it. If not, propose a reasonable period, typically 10 to 15 business days.
  • Distinguish Between Curable and Incurable: While most performance issues like delays are curable, some breaches, such as fraud or a wilful violation of safety laws, are generally considered incurable, and you should state this.
  • State the Consequences: Explicitly state, « Failure to fully cure the specified defaults by 5:00 PM on [Date] will result in the immediate termination of the contract, and we will pursue all available remedies for damages. »
  • Ensure Proper Delivery: Send the notice via registered mail and email to establish irrefutable proof of delivery and receipt.

Only after the cure period has expired without a satisfactory remedy can you issue the final notice of termination. By following this step, you close the last door for the other party to argue you acted unreasonably, cementing your position.

Why Do 95% of Commercial Lawsuits Settle Before Reaching Trial?

The image of a dramatic courtroom battle is largely a fiction in commercial disputes. The vast majority of cases, often cited as over 95%, settle long before a judge ever hears the evidence. The primary reason is not a sudden change of heart or admission of guilt; it is a cold, hard calculation of economic risk. Litigation is extraordinarily expensive, and the outcome is never guaranteed. As a strategic project owner, understanding the economics of litigation is key to managing any dispute.

A significant factor driving settlement in Canada is the « loser pays » costs rule. Unlike in the United States, a losing party in a Canadian court is typically ordered to pay a substantial portion of the winner’s legal fees. While not a full reimbursement, this often ranges from 30-40% or more of the victor’s legal bill. This rule dramatically increases the financial risk of going to trial. Even if you believe you have a 100% winning case, the risk of an unexpected outcome means you could be on the hook not only for your own legal fees but a large portion of the other side’s as well.

The relationship between the amount of a claim and the cost to litigate it is often disproportionate, especially for small to medium-sized disputes. Legal fees can quickly erode or even exceed the value of a potential award. The following table provides a general overview of these pressures in major Canadian commercial hubs.

Cost-Benefit Analysis of Canadian Commercial Litigation
Claim Value Toronto/Vancouver Legal Costs Settlement Pressure Point
$100,000-$250,000 $40,000-$80,000 40% of claim value
$250,000-$500,000 $80,000-$150,000 30% of claim value
$500,000-$1M $150,000-$300,000 25% of claim value
Over $1M $300,000+ 20-25% of claim value

This data, based on analysis from leading firms like Blakes in its guide to litigation in Canada, illustrates why settlement becomes the most rational business decision. Once legal costs are projected to consume a significant percentage of the claim’s value, both parties are heavily incentivised to find a resolution outside of court. Your meticulously built « paper trail fortress » is not just for winning at trial; its primary purpose is to demonstrate the strength of your position so effectively that it forces a reasonable settlement early in the process.

Why Sending a Demand Letter Too Early Can Give the Defendant an Advantage?

After following the careful sequence of reserving rights and providing a cure period, the next logical step seems to be sending a formal Demand Letter, outlining your damages and demanding payment. However, the timing of this letter is a critical strategic decision. Sending it too early can severely undermine your position and hand a significant advantage to the other side. A premature demand letter is often based on estimated, rather than actual, damages and can reveal your legal strategy before you have fully prepared your case.

A savvy defendant will seize on any inaccuracies in an early demand. If you estimate your mitigation costs at $50,000, but can only later prove $30,000, they will use this discrepancy to paint you as unreasonable and your entire claim as exaggerated. This damages your credibility. The better strategy is one of strategic patience. You should only send a formal demand letter after you have a complete and defensible accounting of your actual losses. This includes all costs associated with mitigation, such as hiring a replacement contractor.

As Konata Lake, a partner at Torys LLP, advises in Canadian Lawyer Magazine, the initial approach should be less confrontational:

The aggrieved party should deliver informal, written notification to state their position and invite the counterpart to settle the issue.

– Konata Lake, Partner at Torys LLP, Canadian Lawyer Magazine

This « without prejudice » communication opens the door for negotiation without locking you into a specific monetary demand. The formal, detailed demand letter should only follow once you have built an unassailable case file. The best practice is to wait until your mitigation efforts are substantially complete and documented.

  • Complete Documentation First: Never send a demand until your full file on the breach, cure period, and mitigation efforts is complete.
  • Use « Without Prejudice »: Always mark any preliminary settlement discussions or informal offers as « Without Prejudice, » so they cannot be used against you in court.
  • Wait for Mitigation: Wait until your mitigation efforts are well underway and documented (typically 30-60 days) to have a clearer picture of your actual damages.
  • Calculate Actual Damages: Base your demand on real evidence (invoices from replacement contractors, receipts) not on speculative estimates.
  • Consider Defences: Before sending the demand, anticipate the defendant’s likely arguments and have your counterarguments prepared.

Sending a demand letter is not the opening shot; it is the result of a long, calculated preparation. Sending it at the right time, with irrefutable evidence to back it up, transforms it from a hopeful request into a powerful tool for compelling a favourable settlement.

Key takeaways

  • First, dispassionately assess if the breach is truly « fundamental » and goes to the root of the contract, justifying termination.
  • Immediately send a « Reservation of Rights » letter to acknowledge the breach without waiving your right to act on it later.
  • Before terminating, issue a formal « Notice of Default » giving the contractor a contractually-required (or reasonable) period to cure the failure.

How to Manage Commercial Disputes Without Burning $50,000 in Legal Fees?

The preceding sections have focused on building a case so strong that it forces a settlement, because avoiding a trial is the single most effective way to control legal costs. A $50,000 legal bill can accumulate with alarming speed in a full-blown commercial lawsuit. However, there are several structural mechanisms and strategies available in Canada to resolve disputes more efficiently, well before costs spiral out of control. Your goal should be to leverage these alternatives whenever possible.

One of the most powerful tools is using the appropriate venue. For smaller claims, the Small Claims Court system is designed to be a faster, less expensive alternative to superior court litigation. The monetary limits for these courts vary by province, and recent changes have made them a viable option for increasingly substantial disputes. Understanding your local limit is key to developing a cost-effective legal strategy.

The provincial limits for small claims court offer a streamlined path for many commercial disputes, as shown in this analysis of Canadian court systems.

Provincial Small Claims Court Limits in Canada
Province Small Claims Limit Key Features
Alberta $100,000 Highest in Canada (as of Aug 2023)
Ontario $50,000 Increased from $35,000 in 2025
British Columbia $35,000 Mandatory mediation for $10,000-$35,000
Quebec $15,000 No lawyers allowed in court

Beyond small claims, consider these other cost-management strategies:

  • Arbitration: If your contract contains a well-drafted arbitration clause, this can be a significantly cheaper and faster route than court. Arbitration, which references provincial Arbitration Acts, is private, and the parties have more control over the process and timeline. It is a highly effective tool for resolving disputes without the monumental cost and publicity of litigation.
  • Unbundled Legal Services: You don’t always need to hire a lawyer to manage an entire case. Many firms now offer « unbundled » services, where you hire them for specific, high-value tasks, such as drafting the Notice of Default or reviewing a settlement offer. This allows you to manage the day-to-day aspects of the dispute yourself while getting expert guidance at critical junctures, significantly reducing overall fees.
  • Mediation: A neutral third-party mediator can facilitate a negotiation between you and the other party. Unlike a judge or arbitrator, a mediator does not impose a decision but helps the parties find a mutually agreeable settlement. It is often a mandatory first step in many jurisdictions (like B.C. for certain claims) and has a high success rate.

Ultimately, the most effective way to manage legal costs is to obtain strategic advice before you act. Engaging legal counsel to help you construct your paper trail fortress and follow the correct sequence is not a cost—it is an investment in risk mitigation that can save you hundreds of thousands of dollars in a potential wrongful termination lawsuit.

Rédigé par Rajinder Singh, Commercial Litigator and Dispute Resolution Counsel based in Vancouver. An expert in courtroom advocacy, contract enforcement, and navigating the Canadian judicial system for mid-market enterprises.